After a long construction period, many owners think that things are over and they can finally move in. In fact, at this time, not to take it lightly, because there is a final step in the decoration, acceptance. Acceptance is the only way to move in with peace of mind.
Part.1 wall paint acceptance
How to check and accept
- After the wall paint coating is dried, acceptance by visual inspection and hand feeling under natural light, check that there is no obvious color difference, alkali, color reversion and brush pattern.
- Stand at 1.5m from the wall to observe, check to see if there are sand eyes, color gnashing, drops, color difference, bottom penetration, etc..
- Use the wire connected to the light bulb, the light bulb and the wall ten centimeters apart, shine along the wall to check once, no fallen powder, waves, missed brush, etc.
Acceptance Misconceptions
- Hand touch off the powder has quality problems
During the construction process, there will be dust adhering to the wall, and the powder will fall off when you touch it by hand after construction. In fact, these are just dust, which can be solved by wiping off with a clean towel or duster.
- The smoother the wall surface, the better
The smoother the spray construction, the better. But for roll-on construction, the general roll-off wall will leave roller marks, if the wall is particularly smooth, it may be caused by adding too much water in the paint, and should see if the wall leaves a uniform and detailed knurled print.
Part.2 wallpaper acceptance
Acceptance method: visual inspection or with a strong flashlight
Acceptance criteria: wallpaper spelling to be accurate, fit, no blistering, according to the provisions of the flowers, with a sharp blade cut, there must not be a paper edge torn situation.
Tile acceptance acceptance criteria
- to see whether the brick surface is flat, whether the seam is regular and consistent, whether there is broken, chipped corner phenomenon.
- pay attention to whether the flower tiles and waistline are correctly positioned.
- Pay attention to whether there are empty drums, a small hammer can be used on the wall of each tile gently knock, through the recognition of sound to determine which places have empty drums.
Part.3 Drainage acceptance
- water installation acceptance is mainly to check whether the pipeline is solid, you can open the faucet to check whether it will shake;.
- to see whether the water supply is smooth, there is no leakage, you can take a paper towel wipe to test.
- Check whether there is “flooding” and “backward slope” in the room with floor drains, you can open the faucet or shower, after a period of time to see whether the ground flow is smooth, there is no local ponding phenomenon. 4. should be floor drains, toilets and basins of water is smooth Water test test.
Part.4 electrical box acceptance
- Electric box installation standards provide that the electrical box, switch box should be installed properly, firmly, not inverted, skewed.
- In the case of power failure, hand toggle each switch and leakage protector to check whether the operation is flexible.
- Open the front cover of the electrical box, check whether the wiring of the electrical box is neat, circuit markings are clear, etc.
Part.5 electrical acceptance
- Check the installation of electrical appliances, first turn off the main switch of the electrical box, and then gently shake various electrical appliances by hand to check whether they are loose or fallen.
- Check the accuracy of the installation position of various electrical appliances against the design drawings and the layout of the appliances.
Part.6 door acceptance
- for the site production of wooden doors, should be accepted door opening direction is reasonable, open whether the flexibility, there is no blocking and rebound phenomenon.
- Check whether the door slit is reasonable, wooden doors above and around the door slit can not exceed 3mm, the lower slit is generally 5-8mm.